Construction on Brand Road from SH 190 to Muirfield Road
SUMMARY OF HOA ACTIONS TO DATE
When the HOA Board first became aware of the changes that construction on Brand Road would cause to our entrance at Canterbury Road, we met with the City to better understand the project and get answers to some of our questions. Following those discussions, we created a Entrance Committee and charged the Committee with developing a vision for our entrance along with a plan for its implementation. Karen and Craig Baginski agreed to take on leadership of this Committee.
After consulting with several landscape designers, the Committee selected a landscape design company to help us move forward. Every designer who visited the property agreed that our entrance is in need of an update. We also considered the recent history of our Elm trees. We have been losing approximately one tree per year, at a cost of about $1500 per tree for removal. Given both the ongoing expense of removing these trees and concerns about their long-term survival, we agreed that a comprehensive long-term plan should include replacing the remaining Elm trees with species that have a better survival rate and are better suited to the area.
Cost was an immediate and important consideration. Based on the information available to us, we determined that the City of Garland will absorb a portion of the project cost by replacing landscaping that must be taken out for the Brand Road construction. In addition, we plan to apply for a City of Garland Vitality Grant, and have the option of using a portion of our HOA Reserves, if necessary. Specific financial planning will take place once we receive the completed Landscape Design and have a better understanding of the project's overall scope and cost. At that point, we will be able to determine what improvements can be accomplished immediately and which elements may need to be scheduled and funded over time.
Our goal is to develop a thoughtful, attractive, and sustainable landscape plan that
improves the appearance of our entrance, addresses the changes resulting from the Brand Road
construction, and provides a long-term vision for Canterbury Road.
Projected End Date: March 30, 2028
Start Date: February 26, 2026
CURRENT UPDATES
On October 8, 2026 the Board of Fairways at Firewheel HOA and members of its Entrance Committee met with several representatives of the City of Garland to get specific information about how Canterbury will be affected by the Brand Road Construction. The results of that meeting are summarized below.
Where It All Begins:
Canterbury Road will need to be regraded to a 4% downslope from the front of the first median to Brand Road. To accomodate this, our entrance will be demolished one side at a time - construction will take place on the demolished half, and all traffic will be routed through the other side. The traffic sides as they currently exist will not be wide enough to accomodate turns by school buses, emergency vehicles and large trucks. As a result, we all agreed to the following:
Demolition:
1. The medians and their trees will remain unchanged, including their curbs.
2. Five elm trees will be removed; four on the east side (right side as you are driving in) and one on the west side (left side as you are driving in).
3. The curbs, sidewalks and landscaping will be removed starting at the middle of the first median. They will be cut on a diagonal from the inside edge (the edge closest to Canterbury) and angling to the outside edge (the edge furthest from Canterbury) to the front of the first median. From that point they will be one hundred percent demolished all the way to Brand Road.
4. The "bridge walls" and the lights that are on them will remain untouched.
5. The large rocks that are currently in our landscape will be carefully shifted to a location that will not be disturbed by the construction, so we can use them later.
Restoration:
Click here to see a drawing of this phase of the project on Canterbury.
1. During construction, the traffic lanes will be temporarily asphalted. The final entrance will be concrete.
2. The curbs and sidewalks will be restored after the new paving is completed.
3. Irrigation will be restored in accordance with our landscaping plan after the paving is completed.
4. We will hold a later meeting to discuss the specifics of plant and tree restoration. The City is open to using our landscape plan to guide those decisions. We need to be aware that the replacement trees will not be as large as the demolished trees (probably a 3 - 4" caliper measurement), and areas like the asian jasmine will not be as densely planted.
HISTORICAL OVERVIEW INFORMATION
Click on the Title of each Section to see a map of the projected end result.
From George Bush to River Oaks: There will be two lanes northbound and two lanes southbound, culminating in a roundabout at River Oaks. The roundabout will be larger than the one currently located at Campbell and Brand. Its design is the result of Garland’s research and testing with dual goals of beautifying the roadway and slowing traffic down.
Canterbury Drive, Entrance to Fairways at Firewheel: Southbound Brand will have a separate left turn lane into Canterbury. For turning south onto Brand from Canterbury, there will be a dedicated left turn access lane from Canterbury onto southbound Brand. This will give drivers more room to merge with existing traffic. On the Northbound side, there is also a dedicated right turn access lane to enable drivers to slow down while turning into Fairways at Firewheel.
From Canterbury Drive to Muirfield: At the northeast end of construction, there will be another roundabout, leading to a two lane Brand Road continuing on to Campbell Road.
Manager:
Phone:
Email:
Department
Mike Rozelle
972 . 205 . 2174
mrozelle@garlandtx.gov
Engineering 972 . 205 . 2170
Overview Description: This project is converting approximately 3,300 linear feet of existing two lane roadway to a four lane divided thoroughfare with two (2) roundabouts: one at the intersection of River Oak Parkway and East Brand Road, and the other will be at the intersection of Muirfield Road and East Brand Road. The project scope also includes sidewalks, a multimodal trail, drainage, water, wastewater, illumination layout, signage, markings, hardscape, landscape and irrigation improvements.